EDFC Hadley Project:     April 2008 Photos/Updates    (Worcester, MA)



Hadley Construction Update - April 2008

Hadley Photos (9) - April 2008

Hadley Construction Update - April 2008


April's construction effort was largely focused on demolition. Each floor was effectively gutted down to the original floorboards and brick walls in preparation for construction of the new apartments. The existing elevator shafts and one of the existing stairway shafts was also demolished this month. New roofing material was moved to the roof at the end of the month in preparation of replacing the roof in May.